• I want to thank all the members that have upgraded your accounts. I truly appreciate your support of the site monetarily. Supporting the site keeps this site up and running as a lot of work daily goes on behind the scenes. Click to Support Signs101 ...

Here we go again.. The true test for the LX850 year 2 .

cdiesel

New Member
I believe the 54 tech visits.. Our tech may as well have his own desk next to our 800 here lately..

Is the Zund done too or does it have a couple more weeks(!) of cutting?
 

CheapVehicleWrap

New Member
DONE!!!!

1,087,321 s/f

54 tech visits

4 line filters, 2 full encoder rebuilds, replaced entire platen, 100+ fuses, 2 servo motors, 2 new sets of dual cores, replaced capping assembly twice plus so much more I forgot about.

She limped for a hot minute thank god for backup LX. She did make it..

We start it all over again in November... That should be even more interesting..


That's insane no?
Glad to hear your parking lot wrap is finished. On to lamination now.
 

rjssigns

Active Member
Mad props to Merritt. I would've gone nuts after the first 4 tech calls not the 54th. I think I will start the paperwork for your sainthood.

What about a Scitex XP5500? I believe that is the model my sub has. Bought 2 and built a special building for them. Runs them at 3000sq ft per hour 24/7 365. PM cycles are alternated so they have continuous production.
 

2B

Active Member
With the issues that you had on this run are you going to get a new machine?
If not what are the tactics for the upcoming round
 